Closure Dates: May 13 – May 23 (subject to change based on excavation conditions)
Location: NW Spring Street between Hillside Lane and N Main Avenue
NW Spring Street will remain closed for the rest of this week and all of next week as part of the Spring Street Grading Project. Please plan ahead, use alternate routes, and allow for extra travel time in the area.
Why is this work happening?
The new water main being installed conflicts with the existing gas main. This project involves relocating our infrastructure to resolve that issue.
What will the project accomplish?
By installing a larger gas line on one side of the street, we’ll eliminate the need for gas lines on both sides—improving efficiency and reducing long-term maintenance.
Who’s funding the work?
Northwest Natural (NWN) is covering the cost of relocating their infrastructure.
Traffic Impacts & Detour Info
Spring Street will be closed during work hours. A detour will direct traffic from Hillside Lane to NW Cherry Street and over to Main Street.
Project Contact:
Nathan Frear, Engineering Technical Coordinator
Phone: 971-979-6457
Thank you for your patience and cooperation!